(Ongoing Work)
Line 48: Line 48:
 
|}
 
|}
  
* Collimator 1+2 merge (Chandan)
 
 
* Tolerances
 
* Tolerances
 
** Physics - Done
 
** Physics - Done
 
** Interference with envelopes - Done
 
** Interference with envelopes - Done
 
** Doses on coils  
 
** Doses on coils  
 +
*** [[Optimizing upstream coil shielding]] (Naz)
 
** Clean transport to dump
 
** Clean transport to dump
* [[Optimizing upstream coil shielding]] (Naz)
 
  
 
== Working Group Members ==
 
== Working Group Members ==

Revision as of 19:39, 1 February 2021

MOLLER Wiki
MOLLER page
DocDB
Project
Teleconferences
Bluejeans

Milestones

  1. hybrid/segmented downselect - November 15
  2. collimators (mid- December)
  3. Review irradiation papers by mid-December
  4. beam pipes and enclosures - Start mid-February
  5. 60% Design review to do a prototype (possible spare) March 8th
    1. Freeze design by February 7th (config 9)
    2. collimator 5, 6 dimensions needed
  6. Dates for upstream 60% Fall 2020?
  7. 90% Design (everything!) - CD2/3 Review
    1. DirRev - July 2023
  8. Supports at low radius

Documentation

To be reviewed:

  1. Specifications
  2. Nomenclature
  3. Radiation dose papers
  4. Song sheet

Ongoing Work

text
The MOLLER spectrometer in TOSCA
text
Layout of the hybrid torus conductor

Working Group Members

  • Internal Working Group
    • Ruben Fair (Project lead)
    • Juliette Mammei (collaboration lead)
  • External Working Group
  • Review Committee Members (as needed)




old wiki