IntegrationDaq 230728

From Moller Wiki
Jump to: navigation, search

Back to Main Page >> Data Acquisition Meetings >> Integrating mode DAQ meetings

previous meeting << >> following meeting

Meeting information

 Meeting time:  12:00pm Eastern
 
 Zoom connection information is sent out by email; please reach out to Paul if you don't have the current link.

Agenda

  • Activity updates
  • General discussion

Open Issues to be followed up later

  1. Discussions with M. Pitt & J. Musson to understand the beam monitor signals we'll be getting
  2. Draft timing diagram: DocDB 790
  3. Michael, Bob, Brynne, and Paul should put together a list of the integrator running modes we would like to have available

Minutes

Recording at zoomgov:

Participants: R. Conaway, W. Gu, B. Moffit, P. King, D. Bishop, B. Blaikie, D. Adhikari, B. Shaw, M. Gericke

  • Activity updats
    • Daryl is about 70% finished with the changes to the board. He expects it to take about two more weeks.
      • Michael asks if the new prototype would be available for the September beam test. He'd like to have them by the end of the first week of September
        • Daryl thinks that the turn-around on the boards is about 3 weeks based on another recent project. That means that if he does get the changes done in 2 weeks, it should be back in time
    • Bryerton was busy with another project the past two weeks, but will get updates to his repo for Bryan soon
    • Bryan was also busy with another project. He and Bryerton will follow up
    • Michael reports that Jie now has preamp layouts for either choice of the DC-DC converter, and Dustin is doing low-dose-rate tests with both converters to decide which one we will select
    • Brynne will have some analysis updates next time