Spectrometer
From Moller Wiki
MOLLER Wiki |
MOLLER page |
DocDB |
Project |
Teleconferences |
Bluejeans |
Milestones
- hybrid/segmented downselect - November 15
- collimators (mid- December)
- collimator 1, 2 merge
- hot spots on upstream
- W plate
- optimize the 2-bounce shield (Chandan, Naz)
- collimator 4 (resculpting)
- collimator 5 (including "septapus" for shielding)
- Review irradiation papers by mid-December
- Cip, KK, Kent, Juliette
- Can we live with higher doses on the epoxy than we have been assuming?
- Do we trust the results?
- Are the energies/species close enough?
- beam pipes and enclosures - are major changes required? - Start mid-December
- upstream enclosure and pipes (mid-December)
- clean beam transport due to the SAMs intrusions into the pipe
- Cip has a student designing the SAM intrusions
- aperture in the dump tunnel
- Supports at low radius
- inter-coil supports "under" the envelopes
- now 2-bounce shield is load bearing?
- DS torus "2-bounce" not needed, but septapus for shielding
- Specifications document
- KK and Juliette will look at red text
- We should meet to discuss these
- Nomenclature documented (and used consistently)
Working Group Members
- Internal Working Group
- External Working Group
- Review Committee Members