Back to [[Main_Page|Main Page]] >>  [[DAQ Meetings|Data Acquisition Meetings]] >>  [[DAQ Meetings#Counting mode DAQ meetings|Counting mode DAQ meetings]]
 
Back to [[Main_Page|Main Page]] >>  [[DAQ Meetings|Data Acquisition Meetings]] >>  [[DAQ Meetings#Counting mode DAQ meetings|Counting mode DAQ meetings]]
  
[[CountingDaq_240216 | previous meeting]] <<  >> [[CountingDaq_240315 | following meeting]]
+
[[CountingDaq_240301 | previous meeting]] <<  >> [[CountingDaq_240329 | following meeting]]
  
 
== Meeting information ==
 
== Meeting information ==
Line 15: Line 15:
  
 
==  Minutes ==
 
==  Minutes ==
Recording on Zoom:   
+
Recording on Zoom:  https://jlab-org.zoomgov.com/rec/share/TJcs38L9g5u8D8BW64cCME02phmW-irxQb0BifEWrk9DYIF07QoMO0Di-70rQn9w.0WjEjQd7Bm3LgaUf?startTime=1710521112000
  
Participants:
+
Participants: S. Malace, P. King, R. Michaels, D. Armstrong, S. Chatterjee, B. Blaikie, A. Sen, S. Regmi, B. Moffit, M. Gericke, D. McNulty, H. Liu
 +
 
 +
*  Activity updates
 +
**  Status of the DAQ workspace in the test lab
 +
***  The space has been cleaned up.  There is about a 15'x20' space.
 +
***  Bob says the first things that will be set-up in the test lab will be Hanjie's polarimeter work, and Bob's digital beam monitor tests
 +
**  Simona
 +
***  Worked on single photoelectron test for the pion detector prototype
 +
***  The pion detectors are not using the PMTs that we would use for the experiment.  These were use in the pion detector pre-prototype tested at Mainz.  They used a commercial base.
 +
***  PMT signal is run through a long cable (roughly 75ft) to spread the pulse across several FADC samples.  Want to also check it with a short cable to verify the integrals is the same.
 +
***  Plans to switch this to use a VTP-based trigger next week
 +
***  Running the FADC in sample mode (mode 1) and doing the integrals in analysis
 +
***  Using a pulsed LED as the SPE source for the PMT.  Ran with three different HV settings and several settings of the LED drive voltage.

Latest revision as of 18:07, 15 March 2024

Back to Main Page >> Data Acquisition Meetings >> Counting mode DAQ meetings

previous meeting << >> following meeting

Meeting information

 Meeting time:  1:00pm Eastern
   
  Zoom connection information is sent out by email; please reach out to Paul if you don't have the current link.

Agenda

Minutes

Recording on Zoom: https://jlab-org.zoomgov.com/rec/share/TJcs38L9g5u8D8BW64cCME02phmW-irxQb0BifEWrk9DYIF07QoMO0Di-70rQn9w.0WjEjQd7Bm3LgaUf?startTime=1710521112000

Participants: S. Malace, P. King, R. Michaels, D. Armstrong, S. Chatterjee, B. Blaikie, A. Sen, S. Regmi, B. Moffit, M. Gericke, D. McNulty, H. Liu

  • Activity updates
    • Status of the DAQ workspace in the test lab
      • The space has been cleaned up. There is about a 15'x20' space.
      • Bob says the first things that will be set-up in the test lab will be Hanjie's polarimeter work, and Bob's digital beam monitor tests
    • Simona
      • Worked on single photoelectron test for the pion detector prototype
      • The pion detectors are not using the PMTs that we would use for the experiment. These were use in the pion detector pre-prototype tested at Mainz. They used a commercial base.
      • PMT signal is run through a long cable (roughly 75ft) to spread the pulse across several FADC samples. Want to also check it with a short cable to verify the integrals is the same.
      • Plans to switch this to use a VTP-based trigger next week
      • Running the FADC in sample mode (mode 1) and doing the integrals in analysis
      • Using a pulsed LED as the SPE source for the PMT. Ran with three different HV settings and several settings of the LED drive voltage.