Difference between revisions of "Simulation Meeting February 20 2020 10AM ET"
From Moller Wiki
(Created page with "Back to Main Page >> Simulation Meetings previous meeting << >> Simulation_Meeti...") |
|||
Line 15: | Line 15: | ||
=Attendance= | =Attendance= | ||
− | Attendance: | + | Attendance: Rakitha, Sakib, Dustin, Wouter, Cameron, |
=Minutes= | =Minutes= | ||
− | * | + | * Dustin sends the geometry for shower-max design to match the new ring 5 size. |
+ | * Micheal wanted to know the procedure for signal background deconvolution. Yuxiang did the initial analysis and Ciprian can run the scripts to redo the analysis. | ||
+ | * Background update by Sakib: | ||
+ | ** Deconvolution summary: with the new segmented design we still have higher uncertainty on ep elastic and inelastic background where we have about 60% error now but we need below 20%. | ||
+ | ** The new segmented design shifts background peaks so tiles need to adjust for the offsets in radial. | ||
+ | ** Sakib and Ciprian will try to optimize the ring design and radial detector sizes. | ||
+ | ** Sakib has a script that shows the origins of backgrounds and absolute rates. It gives us a better picture of where backgrounds are coming. He will add neutron rates separately. | ||
+ | ** Raster correlations definition in physics generators were not included but it's in the beam generator. | ||
+ | ** We will have more statistics for the background next week. | ||
+ | |||
+ | |||
<br><br> Return to [[Simulation_Meetings | Simulation Meetings]] | <br><br> Return to [[Simulation_Meetings | Simulation Meetings]] | ||
<br> Return to [[Main_Page|Main Page]] | <br> Return to [[Main_Page|Main Page]] |
Latest revision as of 15:55, 20 February 2020
Back to Main Page >> Simulation Meetings
previous meeting << >> following meeting
Simulation Task List Updated 2019
- Simulation tasks (new)
File:MOLLER Tasks List v8 Sim.doc
Agenda
- Immediate simulation tasks to complete - Ciprian, Sakib, Chandan
Attendance
Attendance: Rakitha, Sakib, Dustin, Wouter, Cameron,
Minutes
- Dustin sends the geometry for shower-max design to match the new ring 5 size.
- Micheal wanted to know the procedure for signal background deconvolution. Yuxiang did the initial analysis and Ciprian can run the scripts to redo the analysis.
- Background update by Sakib:
- Deconvolution summary: with the new segmented design we still have higher uncertainty on ep elastic and inelastic background where we have about 60% error now but we need below 20%.
- The new segmented design shifts background peaks so tiles need to adjust for the offsets in radial.
- Sakib and Ciprian will try to optimize the ring design and radial detector sizes.
- Sakib has a script that shows the origins of backgrounds and absolute rates. It gives us a better picture of where backgrounds are coming. He will add neutron rates separately.
- Raster correlations definition in physics generators were not included but it's in the beam generator.
- We will have more statistics for the background next week.