Difference between revisions of "IntegrationDaq 211201"

From Moller Wiki
Jump to: navigation, search
(Created page with "__NOTOC__ Back to Main Page >> Data Acquisition Meetings >> Integrating mode DAQ meetings In...")
 
 
(3 intermediate revisions by the same user not shown)
Line 2: Line 2:
 
Back to [[Main_Page|Main Page]] >>  [[DAQ Meetings|Data Acquisition Meetings]] >>  [[DAQ Meetings#Integrating mode DAQ meetings|Integrating mode DAQ meetings]]
 
Back to [[Main_Page|Main Page]] >>  [[DAQ Meetings|Data Acquisition Meetings]] >>  [[DAQ Meetings#Integrating mode DAQ meetings|Integrating mode DAQ meetings]]
  
[[IntegrationDaq_211117 | previous meeting]] <<  >> [[IntegrationDaq_211215 | following meeting]]
+
[[IntegrationDaq_211117 | previous meeting]] <<  >> [[IntegrationDaq_220128 | following meeting]]
  
 
== Meeting information ==
 
== Meeting information ==
Line 22: Line 22:
 
# Discussions with M. Pitt & J. Musson to understand the beam monitor signals we'll be getting
 
# Discussions with M. Pitt & J. Musson to understand the beam monitor signals we'll be getting
 
# Draft timing diagram: [https://moller.jlab.org/cgi-bin/DocDB/private/ShowDocument?docid=790 DocDB 790]
 
# Draft timing diagram: [https://moller.jlab.org/cgi-bin/DocDB/private/ShowDocument?docid=790 DocDB 790]
 +
# Michael, Bob, Brynne, and Paul should put together a list of the integrator running modes we would like to have available
  
 
== Minutes ==
 
== Minutes ==
''Recording on Bluejeans.com:''  
+
ParticipantsP. King, C. Cuevas, W. Gu, M. Gericke, J. Pan, R. Michaels, B. Blaikie, J. Fast
  
Participants:
+
*  Update on the integrator.  Both Daryl and Bryerton are out on vacation through the end of the year.  Daryl sent the following set of updates:
 +
**  The problem with the XU1 being fried was related to a power-up sequencing error. This was fixed by removing a part that is not essential to the module operation
 +
**  The two modules at TRIUMF have been modified to correct other minor problems
 +
**  Both ADC boards have been powered up through the POE and external power connections successfully
 +
**  Both ADC boards are booting correctly and are ready for firmware development
 +
**  Not sure if Michael wants to do their own modifications or send them to TRIUMF
 +
**  It's unlikely that Bryerton will make any significant progress on the firmware until next year
 +
*  Other discussion
 +
**  Michael will probably send the other three boards to TRIUMF for the modifications
 +
**  Discussion of the test stand development
 +
***  I have two crates set up at OU and am waiting for the CPUs (expected ~15 DEC).  I have a scaler module and digital gate generator to begin with.
 +
***  Bob talks about the JLab test stand where we have the FADC and VETROC for event mode testing; this will also be shared for Compton DAQ testing
 +
**  I need to get the list of anticipated module counts to Chris; we should then see if we can start to order components, etc.

Latest revision as of 19:41, 26 January 2022

Back to Main Page >> Data Acquisition Meetings >> Integrating mode DAQ meetings

previous meeting << >> following meeting

Meeting information

 Meeting time:  3:00pm Eastern
 
 BlueJeans calling instructions:
 Toll-Free Number (U.S.&  Canada):  888-240-2560 
 Other BlueJeans access phone numbers are listed at https://www.bluejeans.com/premium-numbers
 
 Bluejeans CODE:                    385 600 867
 Bluejeans link: https://bluejeans.com/385600867

Agenda

  • Activity updates
    • Status of 16-ch. integrator firmware development
  • General discussion

Open Issues to be followed up later

  1. Discussions with M. Pitt & J. Musson to understand the beam monitor signals we'll be getting
  2. Draft timing diagram: DocDB 790
  3. Michael, Bob, Brynne, and Paul should put together a list of the integrator running modes we would like to have available

Minutes

Participants: P. King, C. Cuevas, W. Gu, M. Gericke, J. Pan, R. Michaels, B. Blaikie, J. Fast

  • Update on the integrator. Both Daryl and Bryerton are out on vacation through the end of the year. Daryl sent the following set of updates:
    • The problem with the XU1 being fried was related to a power-up sequencing error. This was fixed by removing a part that is not essential to the module operation
    • The two modules at TRIUMF have been modified to correct other minor problems
    • Both ADC boards have been powered up through the POE and external power connections successfully
    • Both ADC boards are booting correctly and are ready for firmware development
    • Not sure if Michael wants to do their own modifications or send them to TRIUMF
    • It's unlikely that Bryerton will make any significant progress on the firmware until next year
  • Other discussion
    • Michael will probably send the other three boards to TRIUMF for the modifications
    • Discussion of the test stand development
      • I have two crates set up at OU and am waiting for the CPUs (expected ~15 DEC). I have a scaler module and digital gate generator to begin with.
      • Bob talks about the JLab test stand where we have the FADC and VETROC for event mode testing; this will also be shared for Compton DAQ testing
    • I need to get the list of anticipated module counts to Chris; we should then see if we can start to order components, etc.