Thursday, December 6, 2018 11am ET
From Moller Wiki
previous meeting << >> following meeting
Logistic information
BlueJeans calling instructions: Toll-Free Number (U.S.& Canada): 888-240-2560 International toll number: 408-740-7256 Bluejeans CODE: 734 609 7559 Bluejeans link: https://bluejeans.com/7346097559
Agenda
- Prototype testing results (Ernie)
- Costing the spectrometer
- Rational for structural support for the coils
- He vs. air
- Upcoming meetings
Minutes
Attendance: Ernie, Jim, Jason, Juliette, Roger, Kent, Ruben, Dave, Probir, Sandesh, KK, Robin
- Prototype testing results
- 37 C predicted - 32 C was the result
- 10 turn coil 30 C expected in another coil: 1938 A (reading meter off front of supply)
- flow meters - tevalin mech. accuracy +/-2% full scale, pressure gauges +/- 1%
- IR and gauges gave the same results
- 24.1 C at little triangle
- you can see the Delta T from inside to outside
- stresses across coil - Delta T of 30 C
- Left on for ~2 hours
- Chiller would climb over time (chiller issue not coil issue)
- How much overhead is there - function of the water flow
- is there thermal runaway? At what point would it be?
- 70 C on coil - never get close to that - depends on inlet temperature
- will be interlocked - never get to runaway conditions
- what about a failed sensor - coil gets plugged up?
- multiple redundant interlocks meters for DeltaT, flow rate, voltage (R changing)
- weren't having flow meters on every cooling path
- could have a temperature monitor on each
- mechanical temp gauges mounted around; very close to the IR gauge
- everything referenced to inlet coolant temperature
- watch exactly where the conductor goes
- How long did it take to reach thermal equilibrium? - 20-30 minutes
- Emissivity settings (0.95) - set as well as bandwidth - compare to reference
- had a confirmation measurement with the mechanical gauge
- 1938 A - long coil - flow 20% low
- but DeltaT is smaller
- no radiation in Hall in the calculations
- still haven't processed everything
- 0.7 m^2, 500 W seems low compared to what was seen
- coil was not uniform temperature
- epoxy temperature - all thermal measurements on epoxy surface
- How do we want to use this?
- Put a check mark on water flow, DeltaT,
- Diagram or sketch
- summary of data
- need a written report
- If you summarize results
- table of data
- diagram
- Ernie's calculations
- Ruben is not going to model this setup
- don't need to do a full simulation
- not a full CFD, but analytical estimates get pretty darn close
- additional tests of prototype until early to mid-January
- rigidity, flatness (don't have laser trackers)
- people can go to observe
- don't want to power all coils in series because of various issues
- write-up complete before December meeting
- Costing the spectrometer
- move to a separate, standalone meeting
- Rational for structural support for the coils - Tolerance question - should look at the effect of individual pieces of the coil
- tolerance should depend on z and radius - need to look at deformations
- azimuthal shift in one of the coils is very benign - we'd end up hitting adjacent coils
- mechanical, dose on coils and stray fields in beamline
- they are setting down their tolerances in a document
- tolerances chart from Thia about how things relate to each other
- Allen produced it from the CAD
- Q2 measurements - 2mm between energizing on and off - don't want a Q2 measurements each time
- 3 supports - normal to their plane if the coil tips it will move the whole coil
- braces between the coils -
- What questions need to be answered at which stage?
- how much has been done?
- how much work still needs to be done?
- those numbers have got to go up?
- still need some iterations
- what's the goal? Fully vetted cost in January
- Magnet review week of the 28th of January
- prototype (manufacturability, water cooling calculations) - how they will be used
- segmented coil design vs. hybrid
- mechanical support - more degrees of freedom for the segmented
- CAD drawings - JLAB has the drawings
- review questions from the last director's reviews
- CD0 - presented a magnet, get questions
- need a plan to answer - timeframe and resources available
- Engineering meeting to go through the costing done by JLAB
- budgetary bids for everything that was designed
- vacuum chamber, coils, supports (budgetary bids by companies)
- week of the 17th - JLAB and MIT get together - afternoon of 17th, morning of 18th
- Tuesday the 18th w/ JLAB at 9:30am
- JLAB may be asked about upper ceiling of the MOLLER cost end of January
- may request funds for MOLLER
- enough to make sure cost doesn't explode?
- Director's Review (late spring - March, April)
- new review of whole project
- do we have a defendable coil
- preliminary cost
- CD1 review
- what do we need for that?
- Magnet review week of the 28th of January
- He vs. air
- work for another 10 days on physics
- don't have a physics design for He
- haven't thought about all the physics implications
- week of 17th - what engineering
- Upcoming meetings
- Costing meeting December 17-18, 2018 at JLAB
- Magnet review week of the 28th of January
- Director's Review late March to mid-April
- CD1 Review
Return to Spectrometer Meetings