Agenda - Upstream

  • SRD - final draft sent to Mike; was supposed to go out for signature
  • TDR
    • broad outline finalized
    • authors/editors confirmed (except Eric)
    • grabbing figures from PDRs - pdf
  • Status of various questions - pdf
    • Cip send collar 0 dims to Dave
    • Sakib check coll 5 z location in is has US faces at 7558 and 7671 mm
    • coll 6 a,b
      • resolve discrepancy between spreadsheet and CAD
      • Chandan will cross-check 6a, b AND 5 at new locations
  • SAM pipe
    • confirm locations of flanges
    • add ring for SAM stubby tube flanges?
    • check detector plane backsplash
  • Other
    • should pitch at least subcoil 3
      • need to check clearances for underbelly plates - what is included in coil inner radius
    • thickness of underbelly plates - can they have gaps (yes, will check with med priority)
    • Meetings needing
      • coil mods from winding
      • field mapping procedure
  • Need to find a new meeting time for the fall

Minutes

Attendance:

  • Upstream
    • water flow on upstream modelled
    • PNID next week
    • upstream failure mode analysis
  • subcoil 3 prototype coming to JLAB
  • SRD - final draft sent to Mike; was supposed to go out for signature
  • TDR
    • broad outline finalized
    • authors/editors confirmed (except Eric)
    • grabbing figures from PDRs - pdf
  • Status of various questions - pdf
    • Cip send collar 0 dims to Dave
    • Sakib check coll 5 z location in sim has US faces at 7558 and 7671 mm
    • coll 6 a,b
      • resolve discrepancy between spreadsheet and CAD
      • Chandan will cross-check 6a, b AND 5 at new locations
  • SAM pipe
    • confirm locations of flanges
    • add ring for SAM stubby tube flanges?
    • check neckdown dimensions
    • bellows is inconel
    • 2-bounce - 175 mm is the radius at which you will begin to see the end of collimator 1
    • check detector plane backsplash
  • Other
    • should pitch at least subcoil 3 (possibly subcoil 2) <-- ??
      • need to check clearances for underbelly plates - what is included in coil inner radius
      • if we pitch it - then collimator 5 can be moved relative to the coil so it stays in the same physical location
    • thickness of underbelly plates - can they have gaps (yes, will check with med priority)
    • Meetings needing
      • coil mods from winding
      • field mapping procedure
  • Need to find a new meeting time for the fall