Agenda

  • Status of envelopes (Chandan)
  • Anything else needed from physicists for PDR?
    • tungsten shields for the DS coils to reduce dose
      • What shield thickness and at which locations - it might be best to pot these shields in with the coils so vendors will need to know this.
    • Dipole moment in the bore
  • Status of prep for PDR


Minutes

Attendance:

  • Status of envelopes (Chandan)
    • Algorithm is working
    • envelopes for what hits detector plane
      • ep done
      • moller soon
    • what gets through the collimators - next couple of days
    • redo "default" to compare to the old method of making envelopes
  • Anything else needed from physicists for PDR (March 8, slides done Mar. 1)
    • tungsten shields for the DS coils to reduce dose
      • What shield thickness and at which locations - it might be best to pot these shields in with the coils so vendors will need to know this.
      • Need to know: what is the downstream dose?
      • Don't need side plates in downstream
      • will probably need cylinders
      • allowable dose - 20-30 MGy vs. 30-40 MGy
      • hasn't looked at the effect of dipole from offset coils (coll 6 handles this effect?)
    • Dose on G10 or G11 'filler plates' for the coil windows
      • probably not an issue for the downstream
      • Need the plot of dose in downstream magnet (epoxy)
    • for the specifications, are we going to do the mapping in the bore
      • for the design review of the spectrometer as a whole...
      • dipole moment in the bore
      • doses have to be considered
      • we know >50 G is unacceptable for the whole length
  • Status of prep for PDR
    • set of coils pending changes manufacturers need to add
    • pre-production prototype