Meeting Information

GEM @ Stonybrook Meeting
Wednesday December 08, 2021
3:30 pm, ET

Agenda

  1. Kicking off the Gem work planning at Stonybrook.

Meeting Disgust

  1. Project background
    • Stonybrook is assigned to construct 12 out of the 28 layers of GEM trackers for the Moller experiment
    • Two prototype trackers to be constructed by late 2022. GEM material (three rectangular sheets) will arrive SBU in early March; frames will arrive later
  2. Sub-tasks (required volunteers, or will be assigned):
    • Clearing out a perimeter in the basement lab, and setting up the cleanroom.
    • Setting latest JLAb DAQ system: CODA, and configure it to be used for calibrating the prototype GEM trackers
    • Setting
    • Manufacturing stage:
      • Manufacturing/stretching GEM sheet and mount to bracket (with glue) inside the clean room (Klaus and Prakhar)
    • Calibration stage:
      • Manufacturing/stretching GEM sheet and mount to bracket (with glue) inside the clean room (Klaus and Prakhar)
  3. Additional equipment needed:
    • Cleanroom
    • Gas system? CO2 and Helium mixture
    • X-Ray gun mounted on arms that move in small stepped