Difference between revisions of "IntegrationDaq 250206"
From Moller Wiki
(Created page with "__NOTOC__ Back to Main Page >> Data Acquisition Meetings >> Integrating mode DAQ meetings In...") |
(→Minutes) |
||
Line 17: | Line 17: | ||
Recording at zoomgov: | Recording at zoomgov: | ||
− | Participants: | + | Participants: B. Moffit, P. King, Z. Ji, R. Conaway, W. Gu, A. Sen, R. Michaels, M. Gericke, B. Blaikie, D. Bishop, S. Chatterjee, J. Pan, D. McNulty, H. Liu, S. Malace, S. Regmi, C. Cuevas |
+ | |||
+ | * Michael & Daryl | ||
+ | ** The two boards kept at TRIUMF have had the connectors changed; they both boot | ||
+ | ** The single-ended module was working, but there seems to have an occasional synchronization issues with the ADC data. This looks like they are firmware bugs | ||
+ | ** On the differential module, they haven't been able to read the data from the board | ||
+ | *** There is some concern that it might be that the new connector isn't installed right, or if it is a different issue. Daryl would like to compare to the boards being fixed by the vendor | ||
+ | ** Michael hasn't heard back on the delivery time on the other 8 boards, but hopes to have them back in a few weeks | ||
+ | ** Daryl says that the assembled boards have been done really well, and he'd prefer that the same assembly house do the rest | ||
+ | * Bryan: he hasn't made more progress yet | ||
+ | ** He had a question about if there is a new rev1 firmware. Michael thinks that he had shared the most recent rev1 firmware | ||
+ | * Chris says Armen has a chassis panel that they could modify to fit Dustin's rev1 board | ||
+ | ** Dustin will be bringing his board on Feb 17, and will hand it off to Armen to fit the chassis | ||
+ | * Arindam | ||
+ | ** CODA is set up for the integration DAQ test stand | ||
+ | ** He and Paul will get a helicity generator and decoder set up in that crate | ||
+ | * Dustin | ||
+ | ** The error messages he was getting in his streaming DAQ are probably just due to how we're reading the streaming data over the 1Gbps connection. Michael says that if he changes the sampling prescale of 10 and that the errors occur at a low rate. Dustin will check in his data is samples are missing when the errors occur. | ||
+ | * Simona and Hanjie have made progress on getting the pion DAQ | ||
+ | * Side discussion about the coda distribution | ||
+ | ** https://code.jlab.org/fedaq/coda/distribution/3/-/releases | ||
+ | ** The CODA distribution should be exported so that all CPUs/VTPs are using the same directories |
Latest revision as of 18:14, 6 February 2025
Back to Main Page >> Data Acquisition Meetings >> Integrating mode DAQ meetings
previous meeting << >> following meeting
Meeting information
Meeting time: 11:00am Eastern Location at JLab: CC F226 Zoom connection information is sent out by email; please reach out to Paul if you don't have the current link.
Agenda
- Activity updates
- General discussion
Minutes
Recording at zoomgov:
Participants: B. Moffit, P. King, Z. Ji, R. Conaway, W. Gu, A. Sen, R. Michaels, M. Gericke, B. Blaikie, D. Bishop, S. Chatterjee, J. Pan, D. McNulty, H. Liu, S. Malace, S. Regmi, C. Cuevas
- Michael & Daryl
- The two boards kept at TRIUMF have had the connectors changed; they both boot
- The single-ended module was working, but there seems to have an occasional synchronization issues with the ADC data. This looks like they are firmware bugs
- On the differential module, they haven't been able to read the data from the board
- There is some concern that it might be that the new connector isn't installed right, or if it is a different issue. Daryl would like to compare to the boards being fixed by the vendor
- Michael hasn't heard back on the delivery time on the other 8 boards, but hopes to have them back in a few weeks
- Daryl says that the assembled boards have been done really well, and he'd prefer that the same assembly house do the rest
- Bryan: he hasn't made more progress yet
- He had a question about if there is a new rev1 firmware. Michael thinks that he had shared the most recent rev1 firmware
- Chris says Armen has a chassis panel that they could modify to fit Dustin's rev1 board
- Dustin will be bringing his board on Feb 17, and will hand it off to Armen to fit the chassis
- Arindam
- CODA is set up for the integration DAQ test stand
- He and Paul will get a helicity generator and decoder set up in that crate
- Dustin
- The error messages he was getting in his streaming DAQ are probably just due to how we're reading the streaming data over the 1Gbps connection. Michael says that if he changes the sampling prescale of 10 and that the errors occur at a low rate. Dustin will check in his data is samples are missing when the errors occur.
- Simona and Hanjie have made progress on getting the pion DAQ
- Side discussion about the coda distribution
- https://code.jlab.org/fedaq/coda/distribution/3/-/releases
- The CODA distribution should be exported so that all CPUs/VTPs are using the same directories