Wednesday Feb 09, 2022<br>
 
Wednesday Feb 09, 2022<br>
 
3:30 pm, ET<br>
 
3:30 pm, ET<br>
Meeting Zoom link: https://stonybrook.zoom.us/j/97131474921?pwd=c3FBN215Z3dyNWdBZS8zc2VNbGJNUT09
+
Meeting Zoom link: https://stonybrook.zoom.us/j/97131474921?pwd=c3FBN215Z3dyNWdBZS8zc2VNbGJNUT09<br>
Indico page: [https://indico.bnl.gov/event/14324/]
+
Indico page: https://indico.bnl.gov/event/14324
  
 
== Project background ==
 
== Project background ==
Line 17: Line 17:
 
# Setting up clean room
 
# Setting up clean room
 
# Moller Simulation (Reemo update)
 
# Moller Simulation (Reemo update)
 +
 +
# Moller Optics meeting [https://moller.jlab.org/wiki/index.php/Optics_Meeting_Feb_8_2022_2PM_ET]
  
 
== Summary and Next Step ==
 
== Summary and Next Step ==

Latest revision as of 20:18, 9 February 2022

Back to GEM @ Stonybrook page


Meeting Information

GEM @ Stonybrook Meeting
Wednesday Feb 09, 2022
3:30 pm, ET
Meeting Zoom link: https://stonybrook.zoom.us/j/97131474921?pwd=c3FBN215Z3dyNWdBZS8zc2VNbGJNUT09
Indico page: https://indico.bnl.gov/event/14324

Project background

  1. Klaus' slides on the Moller GEM is to be added here for reference.
  2. Stonybrook is assigned to construct 12 out of the 28 layers of GEM trackers for the Moller experiment
  3. Two prototype trackers to be constructed by late 2022. GEM material (three rectangular sheets) will arrive SBU in early March; frames will arrive later

Agenda

  1. Setting up clean room
  2. Moller Simulation (Reemo update)
  1. Moller Optics meeting [1]

Summary and Next Step

Task list

  1. Sub-tasks (required volunteers, or will be assigned):
    • Preparation stage:
    1. Clearing out a perimeter in the basement lab (Bill, Vassu, Weibing).
    2. setting up the cleanroom. (Klaus, Bill and others)
    3. Setting up the latest JLAb DAQ system: CODA, and configure it to be used for calibrating the prototype GEM trackers (Bill)
    4. Looking at parsing BigBite data to understand the expected performance.
    5. Simulation to get expected GEM response? (Not a priority right now)
    6. Communicate with machine shop to make a stand for hosting the manufactured prototype based on the CAD drawing (Bill)
    • Manufacturing stage:
    1. Manufacturing/stretching GEM sheet and mount to bracket (with glue) inside the cleanroom (Klaus and Prakhar)
    • Calibration stage:
    1. Operating X-ray gun in in grid and mapping out the efficiency and gain in each sector of the GEM response: efficiency, uniformity, gain, etc (Bill & others)